La Pura Construction Progress Update – October 2026

12/10/2026

As of October 2026, construction continues across La Pura's various components, with several new milestones reached. Progress is as follows: 

La Pura thang 10 (5)
 

  • Zenia

- Wall construction: Progressing to Level 40.

- Exterior painting: Progressing to Level 27.

- Mechanical, electrical, and plumbing (MEP) works: Progressing to Level 33. 

La Pura thang 10 (12)

 

  • Risa

- Wall construction: Progressing to Level 33.

- Exterior painting: Progressing to Level 13. 

La Pura thang 10 (11)

 

  • Lusso Saigon WorldHotels Residences

- Construction: All components have reached Level 11. 

La Pura thang 10 (1)
 

Highlights from La Pura's construction progress in October 2026: 