La Pura Construction Progress Update – October 2026
As of October 2026, construction continues across La Pura's various components, with several new milestones reached. Progress is as follows:

- Zenia
- Wall construction: Progressing to Level 40.
- Exterior painting: Progressing to Level 27.
- Mechanical, electrical, and plumbing (MEP) works: Progressing to Level 33.

- Risa
- Wall construction: Progressing to Level 33.
- Exterior painting: Progressing to Level 13.

- Lusso Saigon WorldHotels Residences
- Construction: All components have reached Level 11.

Highlights from La Pura's construction progress in October 2026: